CEI's Process Optimization Package (POP) for Service & Product Delivery has lots of similarities with the solution to manage capital projects with EPC. This POP for SAP-Primavera integration defines an integrated solution from the contractor's perspective, meaning that high-level project management activities are performed in the SAP-PS (Project System) module of SAP, integrated with the back-end ERP, and more detailed scheduling and execution activities are mostly managed by Primavera. By assuming that sales, budgeting, and procurement activities are performed in SAP ERP, the PS module becomes key to the effective management of the project.

 

buy viagra brampton Characteristics

This packaged solution for SAP-Primavera integration using SAP-EPC has the following characteristics:

Service delivery projects can be managed with SAP PS and Primavera in two ways:
(A) Single-level in that all project structures and associated planning details are duplicated in SAP and Primavera on a 1:1 basis; and
(B) Multi-level in that high-level planning and the master schedule are performed in SAP PS, aligned with Primavera and there then broken out in more details.

  • http://undergroundsf.com/?rav=how-much-does-it-cost-to-get-clomid&3b8=3f The high-level project structure (Master Schedule) is created in SAP based on a sales order.
    A sales order triggers the creation of a high-level WBS and network in SAP. Budgeting and revenue planning are performed in SAP, integrated with related sales, financial accounting and controlling transactions.
  • Viagra Professional Canadian Pharmacy Additional activities and WBS elements may be created in Primavera.
    If more detailed and low-level activities are created in Primavera, they will not be replicated. Their dates, resource assignments, hours, and progress will be summarized to the Master Schedule level.
  • http://cictab.mx/?mex=Zetia-Discount-2014&0c9=96 The Master Schedule may be broken out into multiple sub-projects in Primavera.
    Based on a trigger in SAP, the master schedule may be split into sub-projects in Primavera. This means that detailed schedules may be separately managed by various contractors or departments.
  • http://barrycommercial.com/?quo=Buying-Viagra-Online-Australia&ec8=dc Material (and external services) procurement activities are performed in SAP.
    Materials will be procured through SAP's MM purchasing and MRP modules. The procurement of most materials will not be relevant for schedules, but long-lead items may well be. Materials relevant for scheduling will be transferred to Primavera, other activities will not
  • Can I Buy Zovirax Online Resources will mainly be employees or subcontractors.
    Employees or contracted external services will be assigned in Primavera.
  • Scope changes will be performed in SAP first, then broken down in Primavera.
    Changes to the original scope are considered extensions of the planning effort, therefore to be performed in SAP through the adding or changing of PS WBS elements and activities, and then transferred to Primavera.
  • Earned value-type reporting is important to evaluate project progress.
    Cost may be transferred to Primavera, or date and progress information may be transferred back to SAP so that EVA can be performed in the respective receiving application.
  • Primavera owns the schedule - dates and progress.
    Primavera plays a key role in managing the schedule and related calculation of start times of activities. The calculated dates are fed back to SAP.
  • Progress is to be updated weekly from Primavera.
    Progress information from Primavera will need to be updated into SAP, while service entry hours or time reported in SAP will be sent to Primavera for general reference.
  • High-level resource assignments are defined in SAP, low-level resource assignments (individuals) are done in Primavera.
    Trade resources are defined as work centers in SAP PS, and detailed resources as Human Resources records in the SAP HR module. The work centers are brought into the Primavera resource library from SAP, while the pulling of HR records is optional.

 

reglan cost without insurance Benefits

  • Integration with sales activities, establishing the ability for project reporting in line with client requirements.
  • Clear division of ownership of functional tasks, through the project life cycle.
  • Alignment of project structures and master data on a high level, and optionally on a detailed level also.
  • Contractors can work with Primavera, while procurement, finance and maintenance people work mainly in SAP.
  • High-performance data alignment across applications.
  • Contractors and owners can work in the environment that suits them best (contractors in Primavera, and owners in SAP).

 

http://indianmusicrevolution.com/?ind=Voltaren-Buy-Online&a79=f6 Optional Functionality

The following are some of the optional functionality that can be added to the standard template.

  • Status changes triggered from either application
  • Triggering of new activities from Primavera
  • Breaking of the master project into separate detailed projects
  • Performance optimization using Transfer Manager
  • Transfer of relationships from SAP